| TAMU Agriculture Headquarters |
|
| College
Station, TX |
|
| |
|
|
| |
|
| |
|
| |
|
|
|
|
|
|
|
|
| Description |
|
|
|
|
|
|
|
|
| The Texas A&M Agriculture Headquarters is one of the
premiere projects to fulfill the 2020 mission of the Texas A&M University
System. This project includes the construction of four buildings, underground
utilities, concrete paving, and decorative concrete sidewalk through out the
project. |
|
|
|
|
|
| |
|
|
|
|
|
|
|
|
| Scope of Work |
|
|
|
|
|
|
|
| 48,560 CY of Earthwork |
|
|
25,550 SY of Limestone Base |
|
| 13,155 SY of
Sub-Grade Stabilization |
|
|
3,596 LF of Sewer Line |
|
| 55,150 SF of
Sidewalk Installation |
|
|
2,964 LF of Water Line |
|
| Pavement
Markings & Signage |
|
|
7028 SY of Concrete Paving |
|
| |
|
|
|
|
|
|
|
|
| Project Size: |
653,400 SF |
|
|
Original Cost: |
$2,353,310.00 |
|
| Type of
Construction: |
New |
|
|
Final Cost: |
|
$2,353,310.00 |
|
| Notice to
Proceed Date: |
5/10/2009 |
|
|
Project Manager: |
Shawn Erstrom |
|
| Original
Completion Date: |
7/2/2011 |
|
|
Project Superintendent: |
Martin Jackson |
|
| Actual
Completion Date: |
12/20/2010 |
|
|
BPI's Role: |
|
Sub-Contractor |
|
| |
|
|
|
|
|
|
|
|
| Company: |
|
Skanska |
|
|
|
|
|
|
| Owner
Representative: |
Robert Bedrich |
|
|
|
|
|
| |
|
|
|
|
|
|
|
|
| Company: |
|
Kirksey Engineers |
|
|
|
|
|
| Engineer
Representative: |
Richard Akin |
|
|
|
|
|
|
| |
|
|
|
|
|
|
|
|
| Subcontractors |
|
|
|
|
|
|
|
| Striping |
|
Service Maintenance |
|
|
|
|
|
| |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|