| Lakeway Drive was developed in two phases
simultaneously, One phase was built to service the St. Joseph Hospital, and
the second phase was to service Lowe's at the Corinth Property development.
This 1/2 mile of city roadway was built with strict time restrictions to
allow the new Lowes a certificate of occupany. |
| |
|
|
|
|
|
|
|
| Scope of Work |
|
|
|
|
|
|
| 13,550 CY of Earthwork |
|
2320 LF of
Waterline |
| 122,596 SF of
Concrete Paving |
|
|
4572 LF of Curb & Gutter |
| 14,948 SY of
Lime Stabilization |
|
|
1250 LF of RCP Storm Sewer |
| |
|
|
|
|
|
|
|
| Project Size: |
6 Acre |
|
|
Original Cost: |
$1,010,225.00 |
| Type of
Construction: |
New |
|
|
Final Cost: |
|
$1,010,225.00 |
| Notice to
Proceed Date: |
9/5/2009 |
|
|
Project Manager: |
Landon Alford |
| Original
Completion Date: |
2/1/2010 |
|
|
Project Superintendent: |
Shawn Erstrom |
| Actual
Completion Date: |
2/1/2010 |
|
|
BPI's Role: |
|
General Contractor |
| |
|
|
|
|
|
|
|
| Company: |
|
Manhattan Construction |
|
|
|
| Owner
Representative: |
Lisa Cantrell |
|
|
|
|
|
| |
|
|
|
|
|
|
|
| Company: |
|
Mitchel & Morgan |
|
|
|
|
| Engineer
Representative: |
Veronica Morgan |
|
|
|
|
| |
|
|
|
|
|
|
|
| Subcontractors |
|
|
|
|
|
|
| Landscape |
Conrad's Custom |
|
|
|
|
| Electrical |
Dailey Electric |
|
|
|
|
| |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|