| Barron Rd. | ||||||||||||
| College Station, TX | ||||||||||||
|
||||||||||||
| Description | ||||||||||||
| The Barron Road Widening Phase II project includes
widening Barron Road from a 2-lane asphalt roadway, to a 4-lane concrete roadway with a raised median, bike lanes, sidewalks, curb and gutter, and subsurface storm sewer system between Decatur Drive and Barron Cutoff Road. |
||||||||||||
| Scope of Work | ||||||||||||
| 17,250 CY of Earthwork | 81,210 SF of Sidewalk | |||||||||||
| 434,160 SF of Concrete Paving | 23,978 LF of Curb & Gutter | |||||||||||
| 55,948 SY of Lime Stabilization | 4032 LF of RCP & RCB Storm Sewer | |||||||||||
| Project Size: | 76 Sta. | Original Cost: | $4,175,000.00 | |||||||||
| Type of Construction: | New | Final Cost: | $4,175,000.00 | |||||||||
| Notice to Proceed Date: | 12/15/2010 | Project Manager: | Billy Prewitt | |||||||||
| Original Completion Dat | 2/1/2012 | Project Superintend | Shawn Erstrom | |||||||||
| Actual Completion Date: | 2/1/2012 | BPI's Role: | General Contractor | |||||||||
| Company: | Manhattan Construction | |||||||||||
| Owner Representative: | Lisa Cantrell | |||||||||||
| Company: | Mitchel & Morgan | |||||||||||
| Engineer Representative: | Veronica Morgan | |||||||||||
| Subcontractors | ||||||||||||
| Landscape | Conrad's Custom | |||||||||||
| Electrical | Bayer Electric | |||||||||||